MNRE Revises Guidelines To Boost Small Hydro Power Projects In India

Posted On - 14 June, 2025 • By - Ridhima Gupta

Introduction

Aiming at addressing long-standing sectoral challenges and accelerating renewable energy development, the Ministry of New and Renewable Energy (MNRE) has made major changes to the policies controlling Small Hydro Power projects in India. By means of an Office Memorandum dated May 26, 2025, the ministry has changed important clauses of the original guidelines disseminated in 2009 and 2014, so enabling strategic changes meant to give project developers more freedom while preserving performance criteria.1 These all-encompassing changes show the government’s will to release India’s significant small hydro potential—estimated at 21,533 MW across 7, 133 recognised sites—of which only roughly 5 GW is now operational. The updated framework addresses important pain points that have historically hampered project implementation, including strict generating requirements, inflexible commissioning schedules, and complicated verification procedures, so enabling a more favourable environment for sustainable growth in the small hydro sector.

Explanation (Key Points)

Updated Central Financial Aid Policies

The most significant change in the updated guidelines is the rebuilding of the criteria for releasing balance Central Financial Assistance (CFA), which offers more freedom while maintaining performance responsibility. Under the old system, projects had to routinely reach 80 percent of expected monthly generation for at least three consecutive months to be qualified for balance CFA. The new criteria let projects get balance eligible CFA if they reach 80 percent of expected generation for any one matching month as stated in the Detailed Project Report (DPR). This change addresses pragmatic concerns with seasonal variations, grid connectivity issues, and other operational aspects that might prevent consistent monthly performance.

For projects unable of reaching the 80 percent threshold for any one month, the rules include a proportionate reduction mechanism for the second instalment of CFA. Should a project satisfy either cumulative annual generation for one year or 73 percent of expected generation for three consecutive months, the second instalment will be calculated proportionately. Most importantly, this method only addresses the second instalment computation, so guaranteeing that eligible first payments are unaffected by performance variations. Nowadays, all projects also have to show complete proof of energy generation, including certificates from state electricity boards, power transmission companies, or other approved utilities, so enhancing responsibility and transparency in the process of helping others.

Better control of delay and grace periods

The revised guidelines add a consistent grace period of 12 months from the original planned commissioning date for projects suffering delays resulting from unanticipated events. This clause acknowledges the challenging hurdles hydro project development presents—environmental clearances, land acquisition issues, and occasionally outside of developer influence delays in equipment procurement. Reflecting a sensible approach of risk management, the grace period gives developers more time to overcome reasonable obstacles without immediately running afoul of financial penalties.

Regarding delays outside the 12-month grace period, the guidelines establish a disciplined penalty system designed to promote timely completion in line with real project constraints. Five percent of additional delay will reduce financial support; the maximum reduction capped at fifty percent of the second instalment of qualified CFA after deducting the first fifty percent instalment. This graduated penalty system helps to avoid punitive measures meant to compromise project viability and preserves responsibility. Developers are expected to regularly report expected delays together with comprehensive justifications to the ministry, so ensuring open communication and enabling proactive intervention as required.

Revised Project Completion and Extension Policies

Keeping the focus on timely application of the original framework, the overall project completion schedule remains fixed at five years from the date of contract award. Though, the criteria for grant extension have been significantly changed to better depict project reality and implementation challenges. These days, the MNRE Secretary can review cases-by-case for extensions given projects exhibit at least 50 percent overall physical progress. Acknowledging that early-stage difficulties can significantly influence general project schedules, this represents a significant departure from the past need of over 70 percent progress for extension evaluation.

The revised extension criteria have to show real efforts towards project completion and must show evaluations done especially to evaluate specific circumstances based on justified reasons. Particularly, no extension beyond seven years overall will be allowed, maintaining a strict upper limit to stop endless project delays. Should project completion be delayed outside the approved period, financial support could be limited to funds already released or recalled with interest depending on the specific situation. This system balances responsibility with flexibility to safeguard public investment and provide developers reasonable chances for completion.

Updated Guidelines for Testing and Performance Verification

The guidelines have included differential performance verification criteria depending on project capacity since smaller installations might not call for the same comprehensive testing processes as bigger facilities. Projects with installed capacity of one MW or less will be physically inspected with an eye towards suitable installation and commissioning to ascertain rated capacity and generation at rated load, including 10 percent overloading capability for grid-connected installations or load availability for off-grid connections. This simplified approach reduces administrative load and compliance costs for smaller projects even while it guarantees minimum performance standards.

Projects above 1 MW capacity still require full testing and certification of performance, thus maintaining rigorous standards for more significant public investments shown by larger installations. The approved entities for performance verification now include HRED, IIT Roorkee, Jadavpur University, or any other entity assigned by the ministry, so providing more freedom in certification processes and maintaining technical credibility. This development addresses historical concerns about possible verification process bottlenecks and limited availability of testing facilities.

Restructured CFA Release Milestone Specifications

The revised policies define clear milestone criteria for both first and second instalment CFA releases by giving developers explicit roadmaps for assistance qualifying. Developers must show placement of orders for electro-mechanical equipment, disbursement of half term loan, incidence of 50 percent project cost supported by audited expenditure statements, and achievement of 50 percent project progress certified by the relevant state nodal agency for first instalment consideration. These benchmarks ensure notable project progress before public aid release and provide developers reasonable targets.

Should first instalment be released, the second or last instalment requirements now include three months of generating data, commissioning certificates, utilisation certificates, and audited statements of expenditure based on actual total project expenditure. Moreover, needed are physical confirmation of the project and certification of certificates proving that crucial machinery complies either Indian or international standards. This comprehensive documentation system provides developers with unambiguous direction on necessary compliance policies and guarantees whole project evaluation.

Conclusion

The change in Small Hydro Power Scheme rules by the Ministry of New and Renewable Energy marks a turning point for India’s renewable energy sector since it introduces sensible changes addressing long-standing industry issues while keeping strong performance and responsibility criteria. These changes show the government’s will to provide an environment that supports small hydro development, realising the sector’s vital importance in reaching India’s renewable energy targets and improving grid stability by means of consistent baseload power generation. Key issues that have historically discouraged private investment and slowed project implementation are addressed by the balanced approach taken in these changes: increased flexibility in CFA criteria, grace periods for commissioning delays, and streamlining of verification processes.